Utility Plan Guidance

Utility Plans serve as the foundation planning document for the NFRWQPA planning process. A Utility Plan will need to be approved or conditionally approved prior to (or in conjunction with for non-public entities) consideration of any of the following:
•Site application (for new or expanded domestic treatment works, interceptors not eligible for certification, and lift stations)
•Plan amendment request including service area boundary change
•District formation and designation

The NFRWQPA has developed a Utility Plan Guidance document that provides important information on the requirements of a Utility Plan. This guidance document also includes a checklist which should be completed and submitted with the plan. This checklist helps to ensure that all required information has been included as well as directs the reviewer to the location of the information. Please see link below for the policy and guidance document.

Entities wishing to submit a Utility Plan should contact the NFRWQPA office to determine the number of copies they will need to submit as well as the referral agencies that will need to evaluate the plan. Once a Utility Plan has been submitted it will go through a committee review process. The committee will review the plans for consistency with adopted policies and minimum plan requirements. These committee meetings are held as needed (no set schedule). Once the committee has completed the review process the Utility Plan will be placed on the regular NFRWQPA meeting agenda for consideration. The Committee will present their recommendation on the plan at the meeting.
To download and read the document you must have Adobe Reader.

Utility Plan Policy (pdf)
Utility Plan Guidance (pdf)

Utility Planning Committee Meetings

Shambhala Mountain Center Utility Plan Review Meeting - February 26, 2010 from 10:00 - 11:30 a.m. at the NFRWQPA office located at 545 N. Cleveland in Loveland

Fox Acres Utility Plan Review Meeting - March 4, 2010 from 1:30 - 3:00 p.m. at the NFRWQPA office located at 545 N. Cleveland in Loveland

Utility Plans Under Review

Current Status of Utility Plans Under Review (pdf)

Abbey of St. Wallburga
     Original Submittal
Abbey of St. Walburga Utility Plan November 2009 (pdf)
Utility Plan Review Committee Comment Letter 1-12-10 (pdf)
     Revised Submittal
Abbey of St. Walburga Revised Utility Plan 1-28-10 (pdf)
Abbey of St. Walburga Utility Plan - Revised Appendices 1-28-10 (pdf)
Abbey of St. Walburga Utility Plan - Additional Information 3-4-10 (pdf)
Utility Plan Review Committee Comments 3-4-10 (pdf)

City of Brighton Wastewater Utility Plan & Amendment
     Original Submittal
Brighton Utility Plan Amendment 4-09 (pdf)
Brighton Proposed Wastewater Utility Service Area Map 4-09 (pdf)
     Revised Submittal
Brighton Utility Plan Amendment Revised 5-5-09 (pdf)
Utility Plan Review Committee Comments of 5-5-09 Revisions (pdf)

Colorado State University Pingree Park Campus Utility Plan
     Original Submittal
CSU Pingree Park Utility Plan October 2009 (pdf)
Utility Plan Review Committee Comment Letter 11-20-09 (pdf)

Fox Acres Utility Plan
     Original Submittal
Fox Acres Section 1 Report (pdf)
Fox Acres Section 2 Letters (pdf)
Fox Acres Section 2 Appendix A (pdf)
Fox Acres Section 2 Lagoon Data (pdf)
Fox Acres Section 2 Maps (pdf)
Fox Acres Section 2 Study Data (pdf)
Fox Acres Section 3 Appendix B (pdf)
Fox Acres Section 4 Site Application (pdf)
Fox Acres Section 4 Exhibit C (pdf)
Fox Acres Section 5 Utility Plan Check List (pdf)

City of Greeley Utility Plan Amendment
     Original Submittal
City of Greeley Utility Plan Amendment 1-2010 (pdf)

Town of Keenesburg Utility Plan
     Original Submittal
Keenesburg Utility Plan November 2009 (pdf)
Keenesburg Utility Plan Figures (pdf)
Keenesbury Utility Plan Appendix A (pdf)
Keenesbury Utility Plan Appendix B (pdf)
Keenesbury Utility Plan Appendix C (pdf)
Keenesbury Utility Plan Appendix D (pdf)
Keenesbury Utility Plan Appendix E (pdf)
Keenesbury Utility Plan Appendix F (pdf)
Keenesbury Utility Plan Appendix G (pdf)
Keenesbury Utility Plan Appendix H (pdf)
Keenesbury Utility Plan Appendix I Land Use Map (pdf)
Keenesbury Utility Plan Appendix I Zoning Map (pdf)
Keenesbury Utility Plan Appendix J (pdf)
Keenesbury Utility Plan Appendix K (pdf)
Keenesbury Utility Plan Appendix L (pdf)
Keenesbury Utility Plan Appendix M (pdf)
Utility Plan Review Committee Comment Letter 1-8-10 (pdf)
     Revised Submittal
Keenesburg Revised Utility Plan 1-27-10 (pdf)
Figure 1 Revised 1-27-10 (pdf)
Figure 2 Revised 1-27-10 (pdf)
Figure 7 Revised 1-27-10 (pdf)
Appendix D - Preliminary Effluent Limits 1-27-10 (pdf)
Appendix E - FIRM Map 1-27-10 (pdf)
Appendix F - Map and Correspondance for the RCWSMD Alternative 1-27-10 (pdf)
Appendix J - Sewer Line Map 1-27-10 (pdf)
Appendix L - Keenesburg 2007 to 2030 Budget 1-27-10 (pdf)
Appendix N - Existing Lagoon Hydraulic Profile 1-27-10 (pdf)
Appendix N - Proposed Lagoon Hydraulic Profile 1-27-10 (pdf)
     Additional Submittal Information
Appendix B - Checklists 2-18-10 (pdf)
Appendix D - Preliminary Effluent Limits 2-18-10 (pdf)
Keenesburg Response to Committee Comments 2-18-10 (pdf)

Town of Severance and Saddler Ridge Metro District Joint Utility Plan - On hold pending revisions

Shambhala Utility Plan
     Revised Submittal (replaces original submittal)
Shambhala Revised Utility Plan January, 2010.pdf (pdf)
Shambhala Utility Plan Committee Comments.pdf (pdf)

Upper Thompson Utility Master Plan
     Original Submittal
Upper Thompson Sanitation District Utility Plan Revised July 14, 2009 (pdf)
Upper Thompson Sanitation District Utility Plan Issues Response Summary July 14, 2009 (pdf)
Revised Figure 1-1 (pdf)
Revised Figure 11-3 (pdf)
Appendix M (pdf)
     Revised Submittal
Upper Thompson Sanitation District Utility Plan Revised July 14, 2009 (pdf)
Utility Plan Review Committee Comments 10-2-09 (pdf)
     Revised Submittal
Upper Thompson Sanitation District Response to Committee Issues January, 2010 (pdf)
Upper Thompson Sanitation District Revised Utility Plan January, 2010 (pdf)
Figure 1-1 (pdf)
Figure 2-1 (pdf)
Figure 4-5 (pdf)
Table 11-4 (pdf)
Table 11-7 (pdf)
Utility Plan Committee Comments of 1-22-10 Revisions (pdf)
     Revised Submittal
UTSD Response to Committee Comments 2-18-10 (pdf)
Table 11-4 Revised 2-16-10 (pdf)
Table 11-6 Revised 2-16-10 (pdf)
Table 11-7 Revised 2-16-10 (pdf)

Town of Windsor
     Original Submittal
Town of Windsor Utility Plan November 2009 (pdf)
Town of Windsor Appendices November 2009 (pdf)
Windsor Utility Plan Review Committee Comment Letter 1-27-10 (pdf)
     Revised Submittal
Windsor Utility Plan Response to Committee Comments 2-2-10 (pdf)
Windsor Utility Plan Revised 2-2-10 (pdf)
Windsor Utility Plan Cash Flow Projection 2-2-10 (pdf)
Windsor Utility Plan Reserve Fund Cash Flow 2-2-10 (pdf)
Windsor Utility Plan Sewer Fund 20 Year Budget 2-2-10 (pdf)

Current Utility Plan Review Committee Members (pending confirmation)

Rob Fleck St. Vrain Sanitation District - Chair
Randy Siddens - Boxelder Sanitation District
John Mays - Erie
Chris Bieker - Upper Thompson Sanitation District
Mark Thomas - Weld County